Refurbishment of Trading
Hall
The trading hall was built in 1961 and was officially opened on
the 21st of August 1961. Since then not a lot of money has been
invested into the infrastructure. This lack of investment is now
being rectified with a R12 million refurbishment program. The
refurbishment commenced in September 2007 and will include:
• The construction of new dividing fences
• The installation of new lighting
• The installation of new security cameras
• The installation of new electricity cables and new IT cables
• The painting of the interior of the trading hall
|
|
|
The new market hall fences feature durable concrete bases |
It is anticipated that the refurbishment will be
completed by May 2008
The new fences are in the process of being installed and already
there is a marked difference in the appearance of the trading
hall. The fences have been constructed on-site.
The refurbishment has been welcomed by all stakeholders
|
|
|
The new market hall fences concrete bases were manufactured
onsite. |
|
|
|
In addition to the bases, the metal fences were also assembled
onsite |
|